A great question was posted on scrumdevelopment group, worthy of discussion. The question posed ...
Summary
Their business moves very quickly and, more often than not, any stories
that enter a sprint will have been thought up and written up maybe only
two or three days before a meeting of the stakeholders and the product
owner to decide what the priorities are. Anything that doesn't make it
into the list for them to estimate and add to the sprint will go on the
product backlog, but will generally not be looked at again for a while,
if ever.
Question
To this end, our backlog is ever growing with stories that, in all likelihood, we'll never work on. Based on this, should we even bother with a backlog?
Response
Long backlogs in Lean thinking represent waste. Especially given the picture painted by this use case. Long outdated product backlogs means someone in the organization has to go through it and keep it groomed. The longer the backlog, the longer the time required to keep the backlog updated and if it's really ever used, why bother. Important requirements will always surface again.
I personally hate not recording stories as I am always concerned that a great idea will just get lost and forgotten about. But this does lend to wasteful behavior and work.
In this scenario, it's seems like their just-in-time story elaboration is working well. So I would be inclined to recommend that they drop the notion of a product backlog. Or perhaps triage only really high priority ones onto the backlog.
Thoughts?